Building Project update — May 2025
ACHIEVING MILESTONES
The past month saw us reach four major milestones:
Session named the renovated building the Community Life Center.
The Community Life Center is now empty, ready for construction.
The “Minor Amendment” allowing elevator construction is nearing city approval.
Construction documents are being prepared for our city building permit submission.
We currently expect demolition and asbestos abatement work to begin by mid-July and be completed by mid-September. Pending city approval of our building permit, construction of the new elevator will likely begin in September.
CHAPEL UPDATE
The chapel planning team has developed detailed plans and cost estimates for the renovation of our existing choir and robing rooms.
The first new item for this space, a baby grand piano, has already arrived.
Work on the new chapel will begin this summer.