Building Project Update — February 2025
Progress has continued on the building project during February:
We have informed all building users of the June 1 move-out-by date.
Sara Hunt and Chris Perica completed an inventory of building furniture/items, which includes 367 chairs and 60 tables.
Carolynn Bond and her team have begun culling some books from our library collection.
Carlie Hoskins and Lydia Hunt are disposing of the no longer needed children and youth materials.
Bruce and Jean Lemmon put together the timeline display on the ramp near Shepardson Hall.
Mick McDill has researched line of credit/construction loan options.
We invited the congregation to suggest names for the renovated building.
The chapel planning team led by David Mills has moved quickly to settle on a room configuration and identify many anticipated features.
Having met with the Light and Power, Wastewater, and Floodplain departments, the VFLA architects will submit our minor amendment application to the City on February 26.
Pledges and unpledged donations now total $5.3 million, with $3.1 million already given and earning interest.
If you have questions, ask Dave Campbell or Walt Schuchmann.