Building Project Update — january 2025

An update from the Building Project Organizers

  • We have set a “move-out-by” date of June 1. That means everything that is not bolted down needs to be out of the education building by that time.

  • We have alerted David Dunbar (bells), Carolyn Bond (library), Matthews House staff, and the Scouts to develop move out plans.

  • For the next 6-7 months we will work with VFLA (architect) and Elder (contractor) on detailed design work, city approvals, and refining cost estimates.

  • We expect asbestos abatement work in the education building to begin in June. Abatement is expected to last 6 weeks (two weeks per floor).

  • The current timeline shows full-scale construction activities beginning in late July or August.

  • During January, a site survey and soil sample analysis have been completed to facilitate VFLA’s design work.

If you have questions, ask Dave Campbell or Walt Schuchmann.