Building Project Update — january 2025
An update from the Building Project Organizers
We have set a “move-out-by” date of June 1. That means everything that is not bolted down needs to be out of the education building by that time.
We have alerted David Dunbar (bells), Carolyn Bond (library), Matthews House staff, and the Scouts to develop move out plans.
For the next 6-7 months we will work with VFLA (architect) and Elder (contractor) on detailed design work, city approvals, and refining cost estimates.
We expect asbestos abatement work in the education building to begin in June. Abatement is expected to last 6 weeks (two weeks per floor).
The current timeline shows full-scale construction activities beginning in late July or August.
During January, a site survey and soil sample analysis have been completed to facilitate VFLA’s design work.
If you have questions, ask Dave Campbell or Walt Schuchmann.